PPAP levels define what a supplier physically submits to the customer for production part approval. There are five levels: Level 1 sends only the Part Submission Warrant; Level 2 adds samples and limited supporting data; Level 3 adds samples and complete supporting data; Level 4 sends the warrant plus whatever the customer defines; and Level 5 makes the complete package available for review at the supplier’s site.

The level changes what is sent, not what must exist. For example, a supplier on Level 1 still needs dimensional results, a control plan and a PFMEA on file, because the customer can ask to see them at any time. In this guide, we explain the five PPAP levels, how customers choose them and how to plan for each one. For the details of the most common level, see our guide to PPAP level 3 requirements.

The five PPAP levels in the AIAG PPAP manual are: Level 1 – Part Submission Warrant (PSW) only, plus appearance approval if required; Level 2 – PSW with product samples and limited supporting data; Level 3 – PSW with product samples and complete supporting data; Level 4 – PSW and other requirements as defined by the customer; Level 5 – PSW with product samples and complete supporting data reviewed at the supplier’s manufacturing location. Level 3 is the usual default unless the customer specifies otherwise.

In short: PPAP levels decide how much you send; every level needs the full file ready.

Key points:

  • Five levels: from warrant only (Level 1) to on-site review (Level 5).
  • Default: Level 3 is the usual default in automotive supply.
  • Retention: the complete PPAP file must exist at every level.

What Are PPAP Levels?

PPAP levels are the submission levels defined in the Production Part Approval Process manual published by AIAG. They tell the supplier which documents and samples to send to the customer, and which to keep on file.

The five PPAP levels exist because parts carry different risks. A simple bracket for a well-known supplier does not need the same review as a safety-critical part from a new supplier. Therefore, the customer chooses a level based on part risk, supplier history and its own requirements.

Key Takeaway: PPAP levels control submission, not effort. The same production evidence is needed at every level.

What Does Each of the PPAP Levels Require?

Each of the PPAP levels requires a different submission. The table summarizes what is sent to the customer.

PPAP levels submission package: sample parts, documents and a checking fixture
Level Submitted to the customer Typical use
Level 1 Part Submission Warrant only (plus appearance approval report if required) Low-risk parts, proven suppliers
Level 2 Warrant, product samples and limited supporting data Moderate-risk parts
Level 3 Warrant, product samples and complete supporting data Default for most parts
Level 4 Warrant and other requirements defined by the customer Special cases
Level 5 Warrant, samples and complete data reviewed at the supplier’s site High-risk or critical parts

“Supporting data” refers to the applicable elements of the PPAP element list, such as dimensional results, material test results, process flow, PFMEA, control plan, measurement system analysis and capability studies.

Key Takeaway: Read the purchase order or the customer’s supplier manual for the level. Do not assume it.

How Do PPAP Levels 1 and 2 Work?

PPAP levels 1 and 2 work as reduced submissions for lower-risk parts. The supplier sends less paperwork, but the customer trusts that the full file exists.

Level 1:

  • Submit the Part Submission Warrant
  • Add the appearance approval report for appearance items, if required
  • Keep all other elements on file

Level 2:

  • Submit the warrant and product samples
  • Submit limited supporting data, as the customer specifies
  • Keep the remaining elements on file

For example, a supplier changing a resin lot source for a simple clip may be asked for Level 1. A new revision of a non-critical housing may need Level 2 with dimensional results.

Key Takeaway: At Levels 1 and 2, assume the customer can request any missing element at short notice.

How Does Level 3 Differ From the Other PPAP Levels?

Level 3 differs from the other PPAP levels because it sends the complete supporting data with the warrant and samples. It is the standard level for new parts in most automotive supply chains.

At Level 3, the customer reviews:

  • Dimensional results for every characteristic and cavity
  • Material and performance test results
  • Process flow, PFMEA and control plan
  • Measurement system analysis
  • Initial process studies on special characteristics
  • Appearance approval and samples, where required

Because everything is reviewed, Level 3 is also where most rejections happen. Our article on PPAP level 3 requirements lists the elements and common rejection causes in detail.

Key Takeaway: Prepare every new part as if it were Level 3. Lower levels then become easy.

How Do PPAP Levels 4 and 5 Work?

PPAP levels 4 and 5 work as customer-defined or on-site submissions. They are less common but appear for special or high-risk parts.

Customer and supplier engineers reviewing a running injection molding process on site

Level 4:

  • The customer defines exactly what to submit with the warrant
  • Often used when only certain elements matter, such as material tests
  • Requirements are written in the customer’s instructions

Level 5:

  • The complete package is reviewed at the supplier’s manufacturing site
  • Often combined with a process audit or run-at-rate check
  • Used for critical parts or when the customer wants to see the process

For example, a customer may ask for Level 5 when a safety-relevant part moves to a new supplier, so its quality engineer can see the process running.

Key Takeaway: For Level 5, prepare the production area, records and people, not only the documents.

How Do Customers Choose a PPAP Level?

Customers choose a PPAP level based on part risk, supplier history and their own supplier manual. The choice is normally stated on the purchase order or in the customer-specific requirements.

Common factors:

  • Part criticality: safety or regulatory characteristics raise the level
  • Supplier history: new suppliers usually start at Level 3
  • Type of change: a new part needs more than a minor process change
  • Customer policy: some customers always require Level 3

Customer-specific requirements always come first. In Germany, many automotive customers use the VDA Volume 2 process (PPA) instead of, or alongside, AIAG PPAP, with their own submission rules.

The level can also change during the life of a part. For example, a supplier with a good record may move to Level 1 for minor changes, while a part with field problems may be raised to Level 3 or Level 5 for its next submission.

Key Takeaway: If no level is stated, ask before production. A late level change can delay launch by weeks.

Which Documents Must Be Kept at Every PPAP Level?

The documents that must be kept at every PPAP level are the complete set of applicable PPAP elements. The level only decides how many of them are submitted.

Typical file contents:

  • Design records and engineering change documents
  • Process flow diagram, PFMEA and control plan
  • Measurement system analysis studies
  • Dimensional results and material test results
  • Initial process studies
  • Master samples and checking aids
  • Part Submission Warrant

Gauge studies and capability studies rely on sound measurement statistics. The NIST Engineering Statistics Handbook explains how capability indices compare process spread with specification limits.

Whatever the PPAP levels on the purchase order, a customer audit can ask for any of these documents. Therefore, keep them organized by part number and revision, with the current version clearly marked.

Key Takeaway: Keep the full PPAP file for the life of the part plus the customer’s retention period.

How Should Suppliers Plan for PPAP Levels in a New Project?

Suppliers should plan for PPAP levels at the quotation stage, because the documents need time, parts and measurement capacity.

A practical plan:

  1. Confirm the level and customer-specific requirements in the RFQ.
  2. List the applicable elements and owners.
  3. Plan the run: production tool, material, settings and quantity.
  4. Prepare gauges and run measurement system analysis.
  5. Measure and test: dimensions per cavity, material and performance.
  6. Assemble and review the package before submission.

At WOKE Molds, PPAP, control plans, PFMEA, process flows, FAI and full dimensional or CMM reports are supplied on request when the project requires them. For first-part inspection alone, see our guide to the first article inspection report, and our comparison of PPAP vs FAI.

Key Takeaway: State the PPAP level in the RFQ. It changes lead time and cost, so it belongs in the quote.

FAQ

  • Q: What are the 5 PPAP levels?
    • Level 1 – warrant only; Level 2 – warrant, samples and limited data; Level 3 – warrant, samples and complete data; Level 4 – customer-defined; Level 5 – complete data reviewed at the supplier’s site.
  • Q: Which PPAP level is the default?
    • Level 3 is the usual default unless the customer specifies another level.
  • Q: Do lower PPAP levels need less work?
    • No. The full PPAP file must exist at every level; lower levels only submit less of it.
  • Q: What is the difference between PPAP Level 3 and Level 5?
    • Level 3 sends the complete package to the customer. Level 5 reviews the complete package at the supplier’s manufacturing site.
  • Q: Who decides the PPAP level?
    • The customer, usually through the purchase order or its customer-specific requirements.

Conclusion

PPAP levels decide what a supplier submits, from the warrant alone to an on-site review, but every level needs the full file. Confirm the level early and prepare as if it were Level 3. To plan quality documents for your project, send your drawing and PPAP requirements to our team, and see our quality control and inspection process.